Tantramar council has approved an $84,393 engineering study to determine what repairs and upgrades are needed at the municipality’s wastewater treatment facilities in Sackville, Middle Sackville and Dorchester.
Council heard about the problems at its November 10 meeting. Staff outlined the wastewater issues at all three facilities, including the results of a toxicity test that Middle Sackville failed in 2025. Council later awarded the engineering contract to Englobe Corporation.
“Tantramar has three wastewater treatment facilities, all of which are experiencing issues,” superintendant of public works Michelle Sherwood told council. She said it is believed none of the facilities has been desludged since construction, although that has not been confirmed.
The Crescent Street facility in Sackville is the largest, handling about 4,000 cubic metres of wastewater each day. It dates back to 1971 and has been operating under a transitional authorization since 2015. The authorization gives Tantramar until the end of 2030 to upgrade the facility, which was built before today’s wastewater standards were in place.
Monthly sampling figures show that Crescent Street has exceeded its transitional authorization limit for carbonaceous biochemical oxygen demand 60 times since 2015. The measurement is used to assess organic matter in wastewater and the oxygen needed to break it down. Its limit for total suspended solids was exceeded nine times during the same period.
Middle Sackville’s facility, built in 1980, has also had periodic exceedances of both limits. It failed an acute lethality test in 2025, which caught the attention of Councillor Allison Butcher.
“What is acute lethality? ‘Cause it sounds serious,” Butcher asked.
Sherwood explained that the test involves exposing living organisms to a wastewater sample to see whether they survive. Middle Sackville wasn’t required to undergo the test but staff decided to carry it out anyway. They were already doing the same testing at Crescent Street.
“We did it because we do it at the Crescent Street, and we were just trying to make sure that we had all of our T’s crossed and I’s dotted, and, um, it, it failed drastically,” Sherwood said.
Council heard no further details about the 2025 test. Sherwood did not say whether Middle Sackville had been tested again since then, or what the failure might have meant for the surrounding environment.

Dorchester has had problems of its own. Its wastewater lagoon, built around 1975, has exceeded suspended solids limits periodically over the last few quarters. The facility handles less than 220 cubic metres of wastewater a day, while Middle Sackville handles about 260.
If the problems at those two facilities continue, Sherwood said Tantramar may have to apply for transitional authorizations like the one already in place at Crescent Street.
Before deciding on repairs, Tantramar needs to know more about the condition of the three facilities. The study will help determine what work is needed, how much it could cost and what funding the municipality may need.
Councillor Alyssa Greene wanted to know when the work could be finished. She also asked whether municipal employees could take on some of the assessment, potentially reducing the cost.
“It’s a type of engineering that is not done by just anybody,” Sherwood replied.

Sherwood said municipal technologists were already collecting figures from lift stations to help determine how much wastewater was going into the lagoons. Most of the assessment, however, would be handled by the engineering firm.
Greene also asked about the timeline for the study. Two of the three firms that bid on the contract had proposed finishing in May 2027, while the third gave a later date. Sherwood did not specify a firm completion date for Englobe during the discussion.
The municipality had issued its request for proposals on September 30, with three firms submitting bids by the October 22 deadline. Englobe’s price of $84,393 was the lowest, and it also received the highest evaluation score. CBCL submitted a price of $99,704, while WSP’s bid was $264,920.
Council voted in favour of awarding the contract to Englobe, with no opposition recorded. The $84,393 price is before HST and covers the study only. Any repairs would be a separate expense.
Tantramar won’t know the cost of those repairs until the assessment is finished. Meanwhile, Crescent Street has until the end of 2030 to complete its upgrades, and questions remain about the failed toxicity test in Middle Sackville.